HH55-04 Progress Report

Project manager Thomas Jonsson was joined by VP Bruce Livingstone for the stage two inspection aboard HH55, hull number four and things are progressing well. HH55-04 left the paint booth last week with a newly completed top coat, and is now back on the production floor.
On board HH55-04 several systems are in their final stages of installation, including the electronics and air conditioning, with the trampoline scheduled to go in at the end of the month. Overall everything is on track and looking good with plenty still to to do ahead of next month's soft launch.